Please review the following information for scheduled maintenance details:
UPS Maintenance:
Monday, May 9th, 8:00 AM - 5:00 PM (PDT)
Monday, May 9th, 4:00 PM (GMT) - Tuesday, May 9th, 1:00 AM (GMT)
Tuesday, May 10th 8:00 AM - 5:00pm (PDT)
Tuesday, May 10th 4:00 PM (GMT) - Wednesday, May 11th, 1:00 AM (GMT)
Customer Impact:
There should be no impact to the power in the facility and no down time is expected.
This notice is for advisory purposes only.
Maintenance Details:
The maintenance schedule will be completed in 2 phases.
Monday May 9th - Preventive Maintenance performed on UPS 3 and 4.
Tuesday May 10th - Preventive Maintenance performed on UPS 1 and 2.
---------------------------------------------------------------
Generator Run:
Thursday, May 12th 7:00 PM (PDT) - 11:59 PM (PDT)
Friday, May 13th, 3:00 AM (GMT) Friday - May 13th 8:00 AM (GMT)
Customer Impact:
There should be no impact to the power in the facility and no down time is expected.
This notice is for advisory purposes only.
Maintenance Details:
We will also be performing our quarterly generator run Thursday, May 12th, 2011 from 7:00 pm PST to 11:59 pm PST, the expected time on generator should be approximately one hour, however we need a 5 hour maintenance to ensure we are covered during the duration.
Quarterly Generator Run (test) required to ensure contingent power in case of an outage.
Inquiries:
If there are any additional questions before, during, or following the maintenance, please direct them to the ServePath Support Center via phone or open a case online at http://my.ServePath.com, http://my.ColoServe.com or http://my.gogrid.com.
Thank You for your continuing support with GoGrid.
Sincerely,
GoGrid Data Center Team
Toll-Free 1-877-946-4743
International +1-415-869-7444