Wednesday, March 31, 2010

UPS maintenance April 5th and 6th 2010

Please review the following information for scheduled maintenance details:

Infrastructure Update:

Monday, April 5th, 10:00 am - 5:00 pm (PDT)  
(Monday, April 5th, 6:00 pm - Tuesday, April 6th, 1:00 AM GMT)

Tuesday, April 6th, 10:00 am - 5:00 pm (PDT)
(Tuesday, April 6th, 6:00 pm - Wednesday, April 7th, 1:00 am GMT)

Customer Impact:

There should be no impact to the power in the facility and no down time is expected.

This notice is for advisory purposes only.

Maintenance Details:

The maintenance schedule will be completed in 2 phases.

  1. Monday April 5th  - Preventive Maintenance performed on UPS 3 and 4. Each unit will be put into bypass
  2. Tuesday April 6th  - Preventive Maintenance performed on UPS 1 and 2. Each unit will be put into bypass

 

Inquiries:

If there are any additional questions before, during, or following the maintenance, please direct them to the ServePath Support Center via phone or open a case online at  http://my.ServePath.com or http://my.ColoServe.com.

Sincerely,

ServePath Data Center Team

Toll-Free 1-866-321-PATH (7284)

International +1-415-869-7000